Hi Pete,
This is a basic concept of SFC processing:
- moving and SFC from in work at the current to another operation can be done in different ways;
- if the movement finishes with Complete action or non-confirmance action (Scrap, disposition to NC routing), then it is taken as the original step has been finished;
- if the movemet finishes with another action, it implies that the SFC has been signed off and then moved to the new step, and the original step is not finished;
- the count of pairs "Start-Compete" versus the count of pairs "Start-NC" are used for Operation Yield reports which are basic KPIs for production.
Thus it is expected that if an SFC gets moved from the step with NC action, then there should be no Compete action to ensure that Yield reports are calculated correctly.
Regards,
Sergiy